- Almost 40% through the project.
- 40 workers on site, and growing
- 62 of 64 trusses needing replacement on the Parade Extension have been completed as well as around 250 dock beams.
- This amounts to the renewal of more than 1/3rd of the structure.
- 2//3rds of the decking have been renewed.
- Replacing the trusses on the central section has started as has refurbishment of the Bandstand Pavilion
- Watch out for the Jack Up Barge